Conductor Tensioner Deck

Apache engaged AME to complete the design, drafting and installation of a unique triple slot conductor tensioner (CT) deck.

Project Profile:

Client:
Apache Energy Limited
Location:
Ensco 106, Offshore, Barrow Island
Date:
Aug 2007 - Feb 2008
Project Duration:
7 weeks
Scope:
Design and installation services

Project Summary:

As part of the Reindeer field development, Apache Energy’s drilling campaign required three conductors to be mounted to their respective tensioner units simultaneously. AME also completed structural analysis review of the rig transom, to verify its suitability for the increased operational loads.

The tensioner deck was required to be easily folded up against the rig transom for transport and also certified, for an offshore lift during installation.

Due to the increased mass of the new tensioner deck, the rig cranes were not able to handle the structure. AME’s installation method utilised the rig’s 600T capacity draw works, to lift the deck directly from the supply vessel beneath the rig.