Sapura Acergy engaged AME to complete detailed design and drafting of a flexible lay system, for the Rockwater II.

Project Profile:

Client:
Sapura Acergy
Location:
Montara Field, Northwest Shelf
Date:
Dec 2010 – May 2013

Project Summary:

AME’s scope of work included:

  • Developing a system that met all of SA’s installation requirements for the Montara campaign
  • Design of all interfaces for the Rockwater II deck
  • Development & design of a removable stern access platform, for installing buoyancy modules
  • Installation of risers and umbilicals
  • Design of the structure for installation onto the vessel, in a single lift
  • Preparing all fabrication drawings for steelwork fabrication, in Asia
  • Preparing all documentation for verification by marine warranty surveyor